Depth of soil to remove (excavation).
Depth of fill material needed.
Standard dump truck holds 10 to 14 cu yd.
Your Results
Enter site dimensions and click calculate.
Embed This Calculator on Your Website
Add this free calculator to your blog, website, or CMS with a simple copy-paste embed code.
Introduction
Site contractors who quote earthwork by the square foot without accounting for soil swell routinely underbid hauling costs by 20 to 30 percent. When you dig a cubic yard of common earth out of the ground, it expands to approximately 1.25 cubic yards on the truck because excavation introduces air voids. That swell factor is what drives hauling cost, not the in-place bank volume. According to RSMeans Building Construction Cost Data, common earth has a standard swell factor of 25 percent, meaning a 100 cubic yard cut produces 125 loose cubic yards to dispose of at the dump fee rate. On a 5,000 cubic yard grading job, that gap represents 1,250 tons of additional hauling that never gets priced if you skip the swell calculation. This excavation volume calculator handles cut and fill quantities, applies soil type swell factors, and converts net earthwork to truck loads for logistics and cost planning.
What This Calculator Does
This excavation and earthwork calculator estimates cut volume (material to remove), fill volume (material to add), and net earthwork balance. Enter site dimensions and average cut and fill depths, then select soil type to apply the correct swell factor. Output includes bank cubic yards, loose cubic yards after swell, net import or export requirement, number of truck loads for hauling, and estimated hauling cost.
The Formula
Bank volume is the volume of material in its natural undisturbed state, calculated in cubic feet (length x width x average depth) and converted to cubic yards by dividing by 27. When soil is excavated, it swells: common earth 25%, sand 12%, clay 35%, rock 50%. This swell factor is applied to the cut volume only when calculating hauling quantities. Net earthwork equals cut minus fill in bank cubic yards. A positive number means material must be exported; a negative number means fill must be imported. Truck loads are calculated from the loose (swelled) export volume divided by truck capacity.
Step-by-Step Example
Measure site dimensions and determine depths
Site: 150 ft long by 80 ft wide. Average cut depth from grading plan: 2.5 ft. Average fill depth in low areas: 0.8 ft.
Calculate cut and fill volumes
Cut area: 150 x 80 = 12,000 sq ft. Cut volume: 12,000 x 2.5 / 27 = 1,111 cu yd bank. Fill area (partial): 60 x 40 = 2,400 sq ft. Fill volume: 2,400 x 0.8 / 27 = 71 cu yd bank. Net export: 1,111 - 71 = 1,040 cu yd bank.
Apply swell factor for hauling
Common earth swell factor: 1.25. Loose volume to haul: 1,040 x 1.25 = 1,300 loose cubic yards. Truck capacity: 14 cubic yards (tandem). Truck loads needed: 1,300 / 14 = 93 loads.
Estimate hauling cost
At $85 per load (haul and dump): 93 loads x $85 = $7,905 in hauling cost. Excavation equipment time at $120/hr, 8 hours to cut and load: $960. Total earthwork cost estimate: $8,865 before profit and overhead.
Real-World Use Cases
Residential Building Pad
A site contractor grading a building pad for a new home on sloping terrain needs to cut 800 cu yd and import 200 cu yd of fill. Net export: 600 cu yd bank. Loose: 750 cu yd. At 12 cu yd per load and $75/load: 63 loads x $75 = $4,725 in hauling. Site work quote is built from this number plus equipment time and spread cost.
Foundation Excavation
A concrete contractor excavating a full basement 40 ft x 28 ft by 8 ft deep: volume = 40 x 28 x 8 / 27 = 329 cu yd. After stripping 6 inches of topsoil across the footprint (123 cu yd), total cut: 452 cu yd. Loose: 565 cu yd. At 14 cu yd per tandem: 41 loads. Topsoil stockpiled separately for final grading reduces disposal cost.
Parking Lot Subgrade Preparation
A commercial paving contractor subgrading a 25,000 sq ft parking lot with an average 1 ft of cut and 0.5 ft of fill in low areas: Net export: 695 cu yd. Loose: 869 cu yd. Truck loads: 62 at 14 cu yd each. Adding topsoil strip (6 in over 25,000 sq ft = 463 cu yd) raises total haul to 115 loads. Hauling cost: $9,775 at $85/load.
Comparison
| Soil Type | Swell Factor | Bank to Loose Conversion | Example Application |
|---|---|---|---|
| Sand / Gravel | 1.12 | 100 yd bank = 112 yd loose | Beach, desert, riverbed sites |
| Common Earth | 1.25 | 100 yd bank = 125 yd loose | Typical residential grading |
| Clay | 1.35 | 100 yd bank = 135 yd loose | Heavy clay soils, wet sites |
| Blasted Rock | 1.50 | 100 yd bank = 150 yd loose | Bedrock excavation, quarry work |
Common Mistakes to Avoid
Using bank cubic yards for hauling estimates instead of loose cubic yards. A 500 cu yd cut of common earth generates 625 loose cubic yards on the truck. Hauling 500 loose yards instead means 10 fewer truck loads ordered, resulting in a $850 shortfall at $85/load.
Ignoring topsoil stripping volume. Topsoil is stripped 6 to 12 inches deep before rough grading begins and is stockpiled separately. On a 15,000 sq ft site, a 6-inch strip removes 278 cu yd that must be accounted for in hauling or stockpile area planning.
Assuming uniform cut depth across the site. Real sites have variable grades. Using a single average depth produces estimates within 10 to 15 percent of actuals. For bid-level accuracy, use a grid or cross-section method from survey data.
Forgetting shrinkage on imported fill. When you import fill and compact it, volume shrinks by 10 to 15 percent compared to the loose truck volume. Order fill by the compacted cubic yard needed, not the loose quantity.
Frequently Asked Questions
Accuracy and Disclaimer
Earthwork calculations are estimates based on average depths and simplified rectangular geometry. Actual volumes depend on field survey data, soil types, compaction requirements, and site-specific conditions. This tool is for preliminary planning and budgeting. Use survey cross-sections and professional grading plans for contract-level takeoffs. Consult a licensed civil engineer for sites with retaining walls, drainage requirements, or environmental considerations.
Conclusion
Once you have the net earthwork figure and truck load count, multiply loads by your hauler's per-load rate for a hauling line item. If the project involves a concrete foundation poured after excavation, calculate the concrete backfill volume separately in the Concrete Volume Calculator since fill concrete has different density characteristics than compacted native soil. For parking lot grading that feeds into asphalt paving, use the net graded area in the Asphalt Paving Calculator once final grade elevations are confirmed.
Related Construction & Engineering Calculators
Concrete Volume Calculator
Calculate how many cubic yards or cubic meters of concrete you need for slabs, footings, columns, walls, and other pours. Includes waste factor and cost estimation.
Use CalculatorConstruction & EngineeringMaterial Cost Estimator
Estimate total material costs for construction projects based on quantities, unit prices, and waste factors.
Use CalculatorConstruction & EngineeringLoad Calculator
Calculate structural beam loads, distributed loads, and point loads for basic engineering analysis.
Use CalculatorConstruction & EngineeringUnit Conversion Calculator
Convert between construction units: feet to meters, pounds to kilograms, PSI to MPa, and more.
Use CalculatorConstruction & EngineeringRoofing Calculator
Calculate roofing area, number of shingle bundles or squares needed, and material costs based on roof dimensions and pitch.
Use CalculatorConstruction & EngineeringRoofing Shingle Quantity Calculator
Calculate the number of shingle bundles needed based on roof dimensions, pitch, and waste factor with material cost estimates.
Use CalculatorYou May Also Find Useful
Tax Calculator
Estimate your 2026 federal income tax based on filing status, gross income, deductions, and current tax brackets. See your marginal and effective tax rates instantly.
Use CalculatorFinance & AccountingSalary to Hourly Calculator
Convert your annual salary to an hourly wage instantly. Adjust for hours per week, weeks per year, and overtime to find your true hourly rate.
Use CalculatorFinance & AccountingCommission Calculator
Determine sales commissions based on revenue, rate tiers, and bonus structures.
Use Calculator